About The Project

The Kochi Metro is a rapid transit system, offering smooth transportation solutions to the people of Kochi, Kerala. It has the distinction of being one of the fastest completed metro projects in India as it was opened to the public within 4 years of its construction.

We assisted the project with deep-basement piling work. We completed 300 piles from Aluva to Kalamaserry in just 2 months, hence completing the task well in advance.

Project Highlight

Year 2019
City Kochi, Kerala
Segment Metro
Service Piling, Water Stoppers
Duration 60 days
Kochi Metro 1
Kochi Metro

Challenges faced

  • The piles were in an area that was a dump yard earlier.
  • Major logistical issues were faced while accessing the location.
  • No contractor in India was ready to pick up the project for the longest time.

Solutions provided

  • Our team with experience of working in difficult terrains were able to overcome the logistical challenge.
  • We inserted a 1000/1200 MM diameter pile in soil and rock.
  • Because this was a complex construction in terms of scope of work, our engineers and technicians put their best foot forward to complete the project.